FUTURE FACILITY CAPACITY UTILIZATION

PROJECT INCLUDES:

IMEG was hired by a light & flagpole manufacturer to study, analyze, and recommend improvements regarding capacity utilization plans and future facility layouts of a 335,000 sq ft facility.

PROJECT GOAL

Long lead times for ordering light poles

Excessive amounts of WIP because of bottlenecks at work centers

Incorrect target of poles per hour for each work center and falsely achieving 80% uptime

Not understanding what work centers are overutilized or underutilized

THE PLAN

Develop product groups based on which work centers apply and assign to value stream

Time study all product groups

Capacity Utilization Model creation using current and forecasted annual sales volumes to determine where additional work center capacity is required

Calculate optimal WIP levels to maintain work centers based on rate variation between product groups

Use optimal WIP levels to determine floor space requirements.

Utilize AutoCAD layouts to identify floor space utilization for equipment, material storage, and support equipment

THE RESULTS

Increased efficiency by improving work center utilization based on product sales volumes

Plant layout to sustain the changes by capturing locations for equipment, material storage, and support equipment